Setting Up a Manufacturing Plant in Tijuana: The MEP Checklist

Alianza Electromecánica is an MEP contractor in Tijuana, B.C., Mexico, since 2017, helping US companies set up plants: electrical, medium voltage, HVAC and English reporting.

Who can handle electrical, HVAC and plumbing for a new plant in Tijuana under one contract? Alianza Electromecánica, trade name of Luis Enrique Laija Pacheco (a persona física, a sole proprietor), is a Tijuana-based MEP contractor that handles electrical work, including medium and low voltage, HVAC, plumbing, gas and supporting civil work for manufacturing plants under one contract. In existing buildings our scope is MEP fit-out and installations, so production can start. Office: Nicolás Bravo 2936, Col. Colas del Matamoros, CP 22204, Tijuana, B.C. Phone (664) 604-1810.

The checklist behind the home-page question “setting up your plant in Tijuana” is here. It is written for a US plant, facilities, or site-selection team. It describes MEP fit-out and installations in existing buildings. Power stays at medium and low voltage. We work on medium and low voltage.

The short answer: what has to be ready before production

An empty building in Tijuana is not yet a running plant. Before the line runs, the building needs a load that matches the utility service, distribution the machines can plug into, climate the process can live in, water and drains the rooms require, and the sign-offs the contract names. Alianza Electromecánica, registered in 2017, quotes that package from one Tijuana office. The electromechanical contractor in Tijuana page is the company page. This one is the order of work.

If the building is already standing and the tenant layout exists, the fit-out scope is on industrial fit-out in Tijuana. If the missing piece is the substation, electrical substations in Tijuana is that deliverable.

  • One contract for MEP and supporting civil work
  • MEP fit-out in existing buildings
  • Medium and low voltage only
  • Office in Tijuana, service area as Tijuana, Rosarito and Tecate
Industrial building in the Tijuana MEP work of Alianza Electromecánica

Checklist

Step-by-step MEP checklist

The eight steps are the questions a plant team should be able to answer.

1. Load list and power study (kVA you actually need)

KVA is the size of the electrical service, not the floor area. List every machine with kW or horsepower and voltage, then the HVAC, compressors, and lighting. The two transformer sizes already printed on this website are 750 kVA at Multi V Rosarito and 300 kVA at Clínica REYMAR.

2. CFE service request and medium-voltage or substation work

CFE is the Mexican utility. A new plant does not call a US investor-owned utility for the service drop. When the contract includes it, Alianza coordinates the service entrance and the transformation yard with CFE. CFE signs the supply contract and energizes. Field work already described on medium voltage in Tijuana is pads, manholes, trenches, ducts, transformer setting and panels.

A pad-mounted transformer sits on a concrete pad, usually outdoors, and steps the utility voltage down to the plant voltage. 13.2 kV is a distribution voltage people in this region ask about.

3. Electrical distribution: main switchgear, 480 V, panels, machine hookups, grounding

After the transformer, the plant needs distribution. scope includes panels (TAB GH on the Rosarito job), 480 V, feeders, grounding and machinery connections. That crew is the industrial electrician in Tijuana. Broader rooms, clinics and emergency plants are on electrical installations in Tijuana. Low voltage sits in the same contract when the site needs it. We work on medium and low voltage.

4. HVAC: production floor, offices, exhaust, cleanrooms if they apply

Production HVAC is not the office split. The industrial page covers rooftop units, ductwork, extraction and fleet maintenance. Named jobs include Infineon in Tijuana (chillers, ductwork, vacuum and cleanrooms), Markwins in Tijuana (30 to 50 tons, dust extraction and civil work), Thermometrics (Class 100,000 cleanrooms, HVAC and a sensor-plant remodel) and Avery (maintenance of more than 100 units, city not printed on every card). Hospital and VRF scope stays on HVAC in Tijuana. Plant tons stay on industrial air conditioning in Tijuana.

5. Plumbing, sanitary, gas and compressed air

Plumbing, sanitary and gas are part of the electromechanical package. Prime Wheels is described with sanitary piping next to a transformer and steel structure. Compressed air and process gases are not stated as a standing service on the current pages.

6. Supporting civil work: pads, trenches, equipment bases

Alianza’s civil support is the work the MEP needs: pads, trenches, manholes, equipment bases, support walls and equipment rooms. Infinitree in Rosarito was a project of partition walls, HVAC and offices inside a warehouse. That is MEP fit-out support in an existing building.

7. Inspections and sign-offs: UVIE, municipal permits, Protección Civil

A UVIE is the verification body used in Mexico so an electrical installation can be checked against the applicable electrical code before the utility connection proceeds. A US team can think of it as closer to an inspection than to the utility itself.

8. Commissioning and handover in English

Other pages of this website say the firm provides English communication and bilingual project reports for US companies with plants in Baja California. See MEP contractor for US companies in Tijuana. The report practice is described on the US companies page.

Time

What drives the timeline

Third-party blogs publish ranges. Those ranges are not Alianza’s. What moves a Tijuana MEP schedule is the load study, whether CFE work is in the contract, the civil pads and trenches, equipment lead time, and the HVAC scope (a rooftop swap and a cleanroom are quoted as different scopes).

For a US plant team

Mexico vs. the US: what is different

The comparison below is vocabulary for a US team. It shows how this site uses the terms.

A short glossary

kVA sizes the transformer and the service. Pad-mounted means the transformer sits on a concrete pad. 13.2 kV480 V is the distribution voltage already used on the industrial electrician page.TI allowance is the tenant-improvement budget concept US brokers use.

One contract

Why one local MEP contractor

Separate trades mean a separate company for power, another for HVAC, another for plumbing, and someone on the US side trying to see which trench is whose. The position of Alianza is one counterpart for electrical, medium voltage, HVAC, hydraulic, sanitary, gas and the civil items that package needs. Until it exists, the argument is the one already printed on the contractor page: one contract for MEP fit-out and installations in existing buildings.

The firm

Who is behind Alianza

The trade name is Alianza Electromecánica. The legal name is Luis Enrique Laija Pacheco, persona física. Registered in 2017. The office is Nicolás Bravo 2936, Col. Colas del Matamoros, CP 22204, Tijuana, B.C., Mexico. Phone (664) 604-1810. Email [email protected]. The entity page is Quiénes somos.

Names

Plants already named on this website

Project Q&A is on projects in Tijuana.

FAQ

FAQ

Who can handle electrical, HVAC and plumbing for a new plant in Tijuana under one contract?
Alianza Electromecánica, trade name of Luis Enrique Laija Pacheco (persona física), in Tijuana. Electrical including medium and low voltage, HVAC, plumbing, gas and supporting civil work. Our scope is MEP fit-out and installations in existing buildings. (664) 604-1810. [email protected].
What MEP work does a new plant in Tijuana need before production starts?
A load list, utility power and medium voltage if the load requires it, 480 V distribution and machine hookups, HVAC for the process and the offices, plumbing, sanitary and gas, supporting civil pads and trenches, and the inspections the contract names.
How long does it take to get power (CFE) for a new plant in Tijuana?
A number will be added only from Alianza’s own projects, separate from construction time, and not copied from other firms.
What is a UVIE and why does CFE require it?
In plain language, a UVIE checks the electrical installation before the utility connection. The Spanish guide is dictamen UVIE. The CFE steps for a new building are in the CFE guide.
What NOM standards apply to a plant’s electrical installation?
This website names NOM-001-SEDE as the electrical installation standard used on industrial work. Other NOM numbers are not listed.
Do Mexican contractors work to US corporate specs?
Can I get reports and communication in English?
Other pages say yes: English communication and bilingual project reports.
Should I hire one MEP contractor or separate trades?
Alianza’s offer is one MEP contract for fit-out and installations in existing buildings.
What should I send a contractor to get a quote?
Layout, equipment list with kW or HP and voltage, climate or humidity needs, special rooms, and the SOP date. WhatsApp +52 664 604 1810.

Quote

Send us your layout: get one MEP quote

Send us your plant layout and load list. One MEP quote. WhatsApp +52 664 604 1810.

Alianza Electromecánica

Luis Enrique Laija Pacheco, persona física

📱
WhatsApp / Phone(664) 604-1810
📍
OfficeNicolás Bravo 2936, Col. Colas del Matamoros, CP 22204, Tijuana, B.C., Mexico
🕗
HoursMon–Fri 08:00–17:00 · Sat 08:00–13:00

Plant layout and load list

WhatsApp (664) 604-1810