To get CFE power for a new plant in Tijuana you submit load data, CFE defines the service, your contractor builds the substation and panels, a UVIE verifies when required, and CFE signs the contract and energizes.
Guide by Alianza Electromecánica, an electromechanical contractor in Tijuana since 2017. Medium and low voltage. Phone/WhatsApp +52 664 604 1810.
Step by step
Address or industrial park, estimated load or equipment list, drawings if available, new building or load increase, and the target power date.
CFE reviews the request and defines the service conditions. CFE publishes its requirements for medium-voltage service; check the current version before applying.
Substation or service preparation, panels and grounding, built by your contractor. See electrical substations in Tijuana and medium voltage field work.
The installation is verified against NOM-001-SEDE by an independent UVIE.
The supply contract, any guarantee deposit and the energization are handled by CFE.
Codes
US headquarters often send drawings based on the NEC. In Mexico the installation must comply with NOM-001-SEDE, and that is what the UVIE verifies. Plan time to review the drawings against the Mexican standard before construction.
More for US companies: MEP contractor for US companies in Tijuana and setting up a plant in Tijuana: MEP checklist.
Roles
Projects
Multi V Rosarito: 750 kVA transformer. Clínica REYMAR: 300 kVA.
Coverage and warranty
Office: Nicolás Bravo 2936, Col. Colas del Matamoros, Tijuana, B.C. 22204, Mexico. Since 2017. WhatsApp or phone (664) 604-1810, email [email protected]. Monday to Friday 8:00–17:00, Saturday 8:00–13:00 (Tijuana time).
FAQ
Quote
Luis Enrique Laija Pacheco, persona física